CiCi d'See TWO Whose roll is it anyways? Name that Contract James Bond Bidder Beware!
100
What is a change directive
A written instruction prepared by the consultant and signed by the owner directing the contractor to proceed with a change in the work within the general scope of the contract documents prior to the owner and the contractor agreeing upon adjustments in the contract price and the contract time
100
What is the roll of the contractor?
To provide shop drawings as required in the contract documents
100
What is CCDC2?
A contract with a known price before the contract begins.
100
What is a performance bond?
indemnifies the owner up to the amount of the bond to complete the contract in the event of default (bankruptcy or insolvency) on the part of the contractor.
100
What is period of irrevocability?
Bidders are unable to withdraw their bids during this time.
200
What is provide?
According to CCDC2 this word means to supply and install
200
What is the roll of the owner?
To obtain and pays for development approvals, building permits and permanent easements.
200
What is CCDC 3?
A contract where the contractor is compensated for the actual costs, plus a fee with an agreed-upon maximum price
200
What is labour and materials bond?
Guarantees that claimants (sub-contractors, sub-trades, and suppliers who have direct contracts with the contractor) will be paid
200
What is 4 days?
The amount of days before bid closing that an architect can issue addendum.
300
What is the contact warranty?
Unless extended, this will only last one year from the date of substantial performance.
300
What is the roll of the consultant?
To prepare supplemental instructions
300
What is CCDC5a?
A contract puts the owner is at risk.
300
What is a surety?
a third party which agrees to indemnify the owner against a loss arising from the failure of the contractor to complete project
300
What is a privilege clause?
The lowest of any tender shall not necessarily be accepted
400
What is Indemnification?
The section of a CCDC contract that describes a risk shifting tool in which one party agrees to take responsibility for the liability of the another party
400
What is the roll of the consultant?
To be the first instance, the interpreter of the requirements of the contract documents
400
What is P3?
A contract allows projects to be financed in ways which may not be possible through public methods
400
What is a bid bond?
Guarantees that if the bid is accepted within the time period stated, the contractor will enter into a formal contract with the owner.
400
What is a bid depository?
A facility operated by the local construction association to collect and register bids from sub-contractors and suppliers, and then transmit these sub-trade bids to general contractors.
500
What is the agreement between the Owner and Contractor?
If there is a conflict within the contract documents this section takes priority above all.
500
What is the roll of the owner?
To provide for the coordination of the activities and work of other contractor and owners own forces with the work of the contract
500
What is CCDC 4?
A contract is used primarily for civil engineering work.
500
What is a bid bond?
This bond must be submitted on time for the bid to be considered compliant
500
What if bids come in 15% over budget?
The architect will revise the construction documents and administer the tender call at no additional fee






Bidding and Contract Negotiations Jeopardy!

Press F11 for full screen mode



Limited time offer: Membership 25% off


Clone | Edit | Download / Play Offline